A vehicle battery is constructed for the installation location and the
individual power requirements of the
particular vehicle. These individual power requirements depend on the
motorization and dif
NOTE: Red symbol for pre-delivery check
The vehicle is coded at the end of the assembly line so that the red symbol
for the pre-delivery check is shown
in the Next Service display (same symbol as veh
Necessary preliminary work
Remove FRONT WHEEL
Remove upper wishbone from swivel bearing.
Remove ANTI-ROLL BAR LINK FROM SPRING STRUT
IMPORTANT: Risk of damage!
Secure spring strut against falling out.
Release screws (1).
Fig. 14: Identifying Spring Strut Release Screws
Installation note:
Turn
Notes
Necessary preliminary work:
Cutting cables to length and strip insulation
Special tools for wiring harness repairs.
Spare parts for vehicle electrical system (stop parts and housings):
Sourcing reference: BMW Parts Service.
Refer to Service Information SI 2 04 07 341
1. Crimping stop p