Necessary preliminary tasks
Check wheel bearings
Lift vehicle.
Check wheel with special tool 36 1 030 (measuring fixture) for lateral runout.
Fig. 1: Checking Wheel Lateral Runout Using Special T
Necessary preliminary work
Remove WHEEL
Mount wheel in balancing machine.
To avoid retooling errors, fit the wheel on the balancing machine in the same
way as it is also fitted on the car
(valve
REMOVING AND INSTALLING/REPLACING 12V SOCKET IN CENTER ARMREST
STORAGE COMPARTMENT
Necessary preliminary tasks
REMOVE CENTRE ARMREST STORAGE COMPARTMENT
Remove 12V socket with special tool 61 0 250.
Fig. 279: Removing 12V Socket Using Special Tool (61 0 250)
REMOVING AND INSTALLING/REPLACING 12
DSC Components
DSC Unit
The DSC unit on the F01/F02 essentially uses the same technology as on the
E70/E71.
Versions
The DSC unit comprises the DSC control unit and the hydraulic modulator. The
two are attached to one another
in such a way as to form a waterproof unit.
The repair kits available a