Notes

WARNING: DANGER OF POISONING if oil is ingested/absorbed through the skin! RISK OF INJURY if oil comes into contact with eyes and skin!

IMPORTANT: Adhere to the utmost cleanliness. Do not allow any dirt to enter the hydraulic system.

Do not draw off hydraulic fluid (risk of contamination).

Close off pipe connections with plugs 32 1 270

Recycling

Catch and dispose of hydraulic fluid in a suitable container.

Necessary preliminary tasks

  • Remove FRONT RIGHT WHEEL ARCH COVER REAR SECTION
  • Release front right UNDERBODY PANELLING

To prevent the oil reservoir from running empty, disconnect return line with special tool 13 3 010.

Connecting Lines
Fig. 112: Disconnecting Return Line Using Special Tool (13 3 010)

IMPORTANT: Pressure lines and connections on valve block must be fitted with suitable seal plugs immediately after dismantling!

Release screw (1) and (2) of return line and pull off return line (3).

Tightening torque 37 13 13AZ.

Connecting Lines
Fig. 113: Identifying Screws

Installation note:

Attention:

When tightening screw connection (1), counter support line (2) with pliers (3).

Non-compliance will result in damage to the line (2)! Tightening torque 37 13 14AZ.

Connecting Lines
Fig. 114: Applying Counter Support With Wrench During Tightening Screw Connection

IMPORTANT: When assembling, make sure that in succession only the sealing plugs of the line to be fitted are removed.

When fitting lines, do not tilt connectors (sealing rings!) and connect fully before screwing.

Do not replace sealing rings on hydraulic lines.

Replace affected line if sealing ring is damaged.

After installation:

  • Fill and bleed HYDRAULIC SYSTEM
  • Check pipe connections for leaks
  • Perform INITIAL OPERATION OF ARS

After installation

  • Fill and bleed HYDRAULIC SYSTEM
  • Check line connections for leaks
  • Carry out INITIAL DYNAMIC DRIVE OPERATION

    READ NEXT:

     Electrical Components

     Initial Operation With Test Run Of Dynamic Drive

    NOTE: The Service function Initial operation of Dynamic Drive must be carried out after: Work on the Dynamic Drive system which involved opening hydraulic lines Replacement/Programming/Coding Dyna

     Removing And Installing/Replacing Control Unit For Air Supply System

    IMPORTANT: Read and comply with notes on PROTECTION AGAINST ELECTROSTATIC DAMAGE (ESD PROTECTION). Necessary preliminary tasks Remove ignition key Disconnect BATTERY NEGATIVE LEAD Remove RIGHT LUG

    SEE MORE:

     Adjusting Camshaft Timing On Right Side (N63)

    Notes IMPORTANT: Release central bolts on adjuster only with special tool 11 9 890. Risk of damage to timing drive. If special tool 11 9 890 can not be fitted, it is necessary when releasing the central bolt to grip the hexagon head of the respective camshaft. (cylinder bank 1 to 4) Necessary pre

     Massage function

    Concept Depending on the program, the massage function ensures relaxed muscles and better blood circulation and can avoid fatigue. General information Eight different massage programs can be selected: Pelvis activation. Upper body activation. Full body activation. Back massage. Shoulder massag

    © 2019-2026 Copyright www.bmw7g11.com