BMW 7 Series: Connection Diagram, Vacuum Activation (N63)
.png)
Fig. 462: Connection Diagram, Vacuum Activation (N63)
- Connection (1) Black to exhaust flaps.
- Distribute element (2), vacuum pump/vacuum reservoir (4).
- Vacuum line (3) black to vacuum pump.
- Vacuum reservoir (4) with three connections.
- Connection, vacuum unit (wastegate), bank 2, cylinders 5 to 8.
- Connection, vacuum unit (wastegate), bank 1, cylinders 1 to 4.
- Vacuum hose (7) black/blue to vacuum unit (5) connection to pressure
converter (OUT) bank 2 cylinders
5 to 8.
- Vacuum hose black to vacuum reservoir connection to pressure converter (VAC)
bank 2 cylinders 5 to 8.
- Vacuum hose (9) black/red to vacuum unit (6) to pressure convert (OUT)
bank 1 cylinder 1 to 4.
- Vacuum hose black to vacuum reservoir connection to pressure converter (VAC)
bank 1 cylinders 1 to 4.
REMOVING AND INSTALLING/RENEWING ELECTRIC CHANGEOVER VALVE ON
EXHAUST TURBOCHARGER, RIGHT (N63)
Necessary preliminary work
- Remove right TURBOCHARGER.
Release screws (1).
Remove electric changeover valve (2).
Installation note:
Replace O-ring.
.png)
Fig. 463: Identifying Electric Changeover Valve And Screws
Assemble engine.
Follow diagnosis instruction.
- Complete vehicle
- Powertrain
- Engine electrical system
- Air supply
- Charging pressure control
REMOVING AND INSTALLING/RENEWING HEAT SHIELD AT BOTTOM (N63)
Necessary preliminary work
- Disconnect the BATTERY CABLE FROM THE NEGATIVE TERMINAL.
- Remove FAN COWL with electric fan.
- Remove the ALTERNATOR (not F04).
- Remove both exhaust turbochargers.
- Remove both exhaust manifolds.
Release screws (1).
Tightening torque 11 65 3AZ.
.png)
Fig. 464: Identifying Screws
Release screws (1).
Tightening torque 11 65 3AZ.
Remove heat shield (2) towards top.
.png)
Fig. 465: Identifying Screws And Heat Shield
Release screws (1).
Tightening torque 11 65 3AZ.
IMPORTANT: Risk of interchange on replacement of the heat shield.
Other shields are installed in the N63H and S63 engines.
.png)
Fig. 466: Identifying Heat Shield Screws
Release front screws on heat shield (1).
Tightening torque 11 65 3AZ.
Remove heat shield (1) towards top.
IMPORTANT: Risk of interchange on replacement of the heat shield.
Other shields are installed in the N63H and S63 engines.
.png)
Fig. 467: Identifying Front Screws On Heat Shield
Assemble engine.
READ NEXT:
Necessary preliminary work
Remove both INTAKE FILTER HOUSINGS.
Remove both control sensors.
Release screws (1).
Lift out holder.
Fig. 468: Identifying Holder Screws
Release screw (2).
Tighteni
Necessary preliminary work
Remove left TURBOCHARGER.
Release screws (1).
Remove electric changeover valve.
Installation note:
Replace O-ring.
Fig. 475: Identifying Electric Changeover Valve Scre
Notes
IMPORTANT: Risk of fire if oil lines are leaking.
Risk of mixing up vacuum hoses.
Necessary preliminary work
Remove CATALYTIC CONVERTER , cylinders 1-4
Disconnect plug connection (1) on elec
SEE MORE:
Steering Systems
Implementation of the Integrated Active Steering function has essentially
been made possible by the new ICM
system complex on the F01/F02.
The Servotronic function including valve control is also taken over by the ICM
control unit. That steering
control function is also influence
REPLACING BEARINGS (WHEEL HUB) FOR FRONT WHEEL
Necessary preliminary tasks
Remove BRAKE DISC
Remove FRONT PULSE GENERATOR
NOTE:
Check brake pads and renew if necessary!
Slacken nut (1).
Tightening torque 31 12 2AZ.
Remove tension strut (2) from swivel bearing (3).
Fig. 51: Identifying Ten